As part of the project, we carried out a range of flooring, screeding, atrium and grandstand works with a total area of 20,000 m². In particular, our team developed and coordinated cement-polymer screed and terrazzo samples, ensuring that they met the requirements for durability, safety and aesthetics
For the installation of the high-strength screed and the geometry of the atrium, we prepared the substrates by removing the old repair layers, milling the concrete structure, installing formwork and reinforced mesh, mounting and calibrating the steps. This was followed by priming and application of protective compounds to increase the wear resistance of the installed surfaces
For the installation of poured floors in the lyceum buildings, we installed a polystyrene concrete base, laid a reinforced film and screed of the designed thickness. Then we performed sanding, application of porous filler and hardener, cutting of shrinkage joints and final polishing of the surface. BIM modeling and digital construction management were used during the work to ensure the accuracy of the execution.
To grind the concrete surface of the grandstands, the works included calibration of concrete surfaces, elimination of defects using cast repair compounds, treatment of cracks with epoxy compounds and mechanical grinding to the specified level of #Grit. The final stage was chemical hardening and dedusting to improve the performance of the grandstand areas. Application of laser scanning allowed to achieve high accuracy of surface geometry
All works were carried out in strict compliance with design standards and with the use of innovative solutions, which ensured high quality of the final result