Lesta Games underground parking lot.

Object
Lesta Games underground parking lot.
Area
1 800 м²
Year of realization
Parking-grade flooring

The three-level underground parking lot of the historic building on Izvestkoviy Lane is part of the modern office of Lesta Games. The space combines engineering functionality and modern design, providing comfort and technology

To create a durable and dust-free coating, resistant to the constant load of the parking lot and visually expanding the space with low ceilings. The work had to be completed within a tight timeframe - during the New Year holidays, so as not to interrupt the operation of the facility

Compliance with deadlines. The works were organized in such a way as to fully complete the repairs during the New Year holidays without disrupting the schedule of the parking lot operation

The mirror effect of the coating. Particular attention has been paid to polishing to a high gloss, allowing the space to be visually enlarged

Work Safety. All stages were performed with minimal dust to avoid triggering fire alarms

Durability and wear resistance. We have created a coating that is resistant to stress and mechanical influences, which does not peel off and does not require complicated maintenance

Functionality on ramps. Highly filled epoxy-quartz non-slip compound for better traction on sloping areas

Rough mechanical sanding and leveling of the floor

Treatment of cracks and defects with a special technological composition

Mechanical polishing for perfect smoothness

Chemical polishing and protection for increased durability and aesthetic shine

Repair of tile joints

Application of markings/navigation in accordance with the customer's requirements

Application of special impregnation followed by filling with quartz sand

Industrial floor repair

A detailed schedule was drawn up for the project together with the customer, which allowed all works to be carried out during the New Year holidays without interrupting the operation of the parking lot. Particular attention was paid to the sequence of stages and precise coordination of activities to meet the deadlines and keep the site clean

The base coat underwent several stages of processing: first, a coarse grinding with metal was performed to smooth the surface and remove defects. This was followed by plastic polishing with a gradual increase in grit to 1500 Grit, after which a protective compound was applied and chemical polishing was carried out to ensure a mirror-like shine and high durability of the coating. At the same time, potholes and cracks in the coating were repaired

Next, the team moved on to the ramps between floors: they were sanded using specialized machines with metal nozzles, dusted, coated with epoxy and filled with quartz sand. This solution created a durable anti-slip coating. Safe and easy to use

Our clients
WUNDERPARK
wunderpark
ETM
ETM
X5 RETAIL GROUP
X5 RETAIL GROUP
VDNKH
VDNKH
SAMSUNG
SAMSUNG
ZEAL MUSEUM OF ART
ZEAL MUSEUM OF ART
Primakov School
Primakov School
TECHNOLOGY CENTER IM. V. I. DOLGIKH
TECHNOLOGY CENTER IM. V. I. DOLGIKH
LG ELECTRONICS
LG ELECTRONICS